The plan is a Google Sheet. Steer it like a project.

Your client will not install a planning tool for you, and the plan has to live somewhere they can open, comment on and print. So it lives in a Sheet. tabviz creates that Sheet in your Drive, already shaped for a plan, and draws it as a Gantt with real dependencies. When the data migration slips a week, you drag one bar and every task after it moves, in the Sheet, under your name.

Start a plan Or try the sample below first. Nothing is saved.
Try itDrag Configuration, sprint 1 to the right. Sprint 2, the integration tests, the go/no-go, the cutover and the go-live follow, and the critical path (red outline) is recomputed. Drag the right edge of a bar to change its end. Drag the small dot at the end of a bar onto another one to link them. Click a date in the table and type another one (yyyy-mm-dd).

Dependencies, written the way you already write them

One column, Depends on, with task numbers. A few letters if you need more than "after the end of".

In the cellMeans
3Starts after task 3 ends
2, 3Starts after both end
8+2Two days after task 8 ends
13SSStarts the same day as task 13
5FF-1Ends one day before task 5 ends

Durations and lags count working days by default, Monday to Friday. One setting switches to calendar days. A milestone happens at the end of its day, so what follows starts the next morning.

The critical path, computed from the Sheet as it stands

tabviz runs the forward and backward passes on your dates and outlines in red every task with no slack. Click a task: the side panel says how many days it can slip, what comes before it and what waits for it. When someone typed a date in the Sheet that breaks a link, the arrow turns red and one button pushes the late tasks to where they can actually start.

Moves only push forward. A task is never pulled earlier behind your back: if a predecessor finishes early, you decide.

Monday's status deck

Copy image puts the whole plan on the clipboard as a sharp PNG, whatever the zoom on screen. Paste it in the weekly status slide and move on. A clean view with nothing but the chart is there for screenshots, and the time scale switches between days, weeks and months.

Nothing to set up on the client's side

What it does not do yet

No resource levelling, no baseline to compare against, no start-to-finish links. It is a prototype from November 2026, not reviewed yet. It runs in Patrice's gtools lab with a Google sign-in that is still in testing mode.