For project leads in consulting
The plan is a Google Sheet. Steer it like a project.
Your client will not install a planning tool for you, and the plan has to live somewhere they can open, comment on and print. So it lives in a Sheet. tabviz creates that Sheet in your Drive, already shaped for a plan, and draws it as a Gantt with real dependencies. When the data migration slips a week, you drag one bar and every task after it moves, in the Sheet, under your name.
yyyy-mm-dd).
Dependencies, written the way you already write them
One column, Depends on, with task numbers. A few letters if you need more than "after the end of".
| In the cell | Means |
|---|---|
3 | Starts after task 3 ends |
2, 3 | Starts after both end |
8+2 | Two days after task 8 ends |
13SS | Starts the same day as task 13 |
5FF-1 | Ends one day before task 5 ends |
Durations and lags count working days by default, Monday to Friday. One setting switches to calendar days. A milestone happens at the end of its day, so what follows starts the next morning.
The critical path, computed from the Sheet as it stands
tabviz runs the forward and backward passes on your dates and outlines in red every task with no slack. Click a task: the side panel says how many days it can slip, what comes before it and what waits for it. When someone typed a date in the Sheet that breaks a link, the arrow turns red and one button pushes the late tasks to where they can actually start.
Moves only push forward. A task is never pulled earlier behind your back: if a predecessor finishes early, you decide.
Monday's status deck
Copy image puts the whole plan on the clipboard as a sharp PNG, whatever the zoom on screen. Paste it in the weekly status slide and move on. A clean view with nothing but the chart is there for screenshots, and the time scale switches between days, weeks and months.
Nothing to set up on the client's side
- In your Drive, shared like any Sheet. tabviz creates the plan in your Drive. Share it with the client from Sheets: editors can edit, viewers only view, in Sheets and in tabviz alike.
- Shaped for a plan. Start and End are dates, Progress a percentage, Milestone a checkbox, Depends on plain text, the header frozen. When the client types in Sheets, the plan stays readable for the chart.
- Your formulas. Turn End into a formula on a Duration column if you like: tabviz then writes the duration and leaves the formula alone.
- One pen. While you edit, the client's PMO sees your name and "is editing since 10:42" instead of fighting over the same cells. If a laptop closes mid-edit, the pen comes back on its own within five minutes.
What it does not do yet
No resource levelling, no baseline to compare against, no start-to-finish links. It is a prototype from November 2026, not reviewed yet. It runs in Patrice's gtools lab with a Google sign-in that is still in testing mode.